For best print
results, set margins to .75" top & bottom and .5" left &
right
USE BACK
BUTTON TO RETURN TO INTERNET
January
23, 2003 Meeting
hosted
by
Public
Works Director Thomas O'Loughlin and Town Engineer Warren Hall
The
following is a transcript made by listening to a videotape of the event. I have never before transcribed such a recording and I freely
admit to being a rank amateur at transcription. Consequently there may exist some errors in the transcription and
I apologize if such is the case. In an
effort to minimize mistakes, I submitted copies of these transcripts to Mr.
O'Loughlin for review by himself and Mr. Hall.
Most of the video tape was audible but there were sections that were
either inaudible or undecipherable and these were omitted. Transcribed by Ronald G. Santa.
1) QUESTION: Are we on hold
now because of the weather?
HALL: Yes, too cold for anyone to get out there and work,
material is freezing, machines are not operating properly, and that is what we
are holding for. I spoke to the
contractor today and he might be here as early as tomorrow. It is supposed to be in the 20s tomorrow so
he’s looking forward to getting back here and doing some more work.
2) QUESTION: Does he have an
estimated completion date or is there a date on the contract that he has to
complete by?
HALL: The answer is yes.
He has 180 days to complete the entire project. The entire project is Turner Road, Wolcott
Avenue, Easton Terrace, Judith Court, and a little portion of Center Avenue.
3) QUESTION: Are there
penalties associated with not meeting the completion date?
HALL: There are no penalties associated with them completing
on time. There will be action taken by
the Town if it is not done in a reasonable amount of time.
4) QUESTION: Are they going
to continue or are they going to stop for a certain amount of time?
HALL: The answer is that they are going to continue depending
upon the weather. They may be back
tomorrow. If it stays in the 20’s they
are going to continue to work.
5) QUESTION: Are they going
to continue the drainage or are they going to go back and start the water at
the other end.
HALL: They are going to continue with the drainage. Once they complete the drainage all the way
to Green End then they are going to go back and do the water.
6) QUESTION: You said this
was going to be done in 180 days?
HALL: Yes, 180 working days.
7) QUESTION: From when? From today?
HALL: No. He started
on October 7th.
8) QUESTION: I’m concerned
because I have a nursery on that road.
We are going to be getting busy with trucks and orders come the middle
of March and I’m concerned about what’s going to happen. How are my customers going to get to my
place of business?
HALL: That is an issue we will have to work out during those
days when your customers are coming in.
We will have to leave a lane open for them to get by.
9) QUESTION: That is
impossible for me to know when they are going to be coming in.
HALL: The road is closed but I want to say that if we tell the
contractor to make it passable for a situation like that, he will accommodate
us.
10) QUESTION: On that water
line, is it going to be tied into Gaudet School? Because we have a hydrant at the Gaudet School which is a dead
end. That should be tied into the 12”
water supply.
HALL: No, there isn’t any plan to tie into the Gaudet
School. It is going to be tied into
Ward Avenue up to Columbia Road. And it
is also going to be tied into Green End and at Wyatt.
11) QUESTION: That hydrant
would have a lot more pressure off this 12” than we have off the other end
HALL: I agree with that.
There are different lines up there.
Some of them are high pressure and some are low pressure
12) QUESTION: Wasn’t there a
hydrant there by the street next to Wick’s property years ago? I thought the line froze and they abandoned
that line.
HALL: I don’t know that.
I’ve got Chief Carlise here.
CHIEF CARLISE: I’ve never seen a hydrant there. No.
There is one by the State garage.
13) QUESTION: From a scheduling
standpoint, I know weather is a factor right now but what is completed? What is coming? When is it coming? What
can be finished? And what is going to
be going on in front of the properties?
Water line – when is that going to start?
HALL: Depending on the weather, I would think that if we
wanted to lock the contractor into a schedule he would say wait a minute I’m
not going to get busy down there until March 1st. Right now he is just kind of peddling away
at it and picking away at it as best he can.
Which is fine. Come March 1 he’s
going to have to start back on the storm drain. He probably has two weeks left on the storm drain. Two weeks to complete the storm drain. After the storm drain, say another three
weeks to complete the water, that’s five weeks. That gets us into the middle of April. Now he’s got to grind the
road, reclaim it, shape it, compact it.
That’s five days there. He
should be off Turner Road by the first or second week in May.
14) QUESTION: Is that 180
days for Turner Road or for the whole contract?
HALL: The 180 days is for the whole contract.
15) QUESTION: Wolcott and
Easton Terrace is yet to do? Is there
much to do over there?
HALL: No, the scope of work is not as much as Turner
Road. Road resurfacing and a little bit
of drainage.
16) QUESTION: Is there a
reason for the fact that they have been doing work so intermittently like down
at Wyatt Road and up by Hoogendorn and back and forth?
HALL: They jump around a few times because of a problem
getting the structures, the catch basins that go in the ground. He had to order those, he had lead time on
those and for some reason that is how they were arriving and he was kind of hop
scotching back and forth.
17) QUESTION: Will the
drainage and water be on the same side?
Is that the west side?
HALL: When it gets down in front of your home down there,
yes it will be.
18) QUESTION: How far will
they be apart?
HALL: The drainage and water pipes will be about two feet
apart
19) QUESTION: You can’t put
them in at the same time in that area.
Dig only one trench?
HALL: We might be able to do that. We might be able to put them in the same trench.
20) QUESTION: Storm drain
and water pipes in the same trench?
They are never going to approve that.
O'LOUGHLIN: Only two feet apart, they are basically going to
be in the same trench anyway. The
reason he hasn’t started the water anyway is that obviously the water decision
was delayed and it was the situation that we had to get the City of Newport
approval before he could even get started.
Otherwise if we had the approval we would have already been working on
it.
21) QUESTION: Has it already
been approved?
HALL: Yes it has. We
have the approval to go ahead with the water.
22) QUESTION: Who is paying
for the water? What about those of us
who already have sewer?
O'LOUGHLIN: We can’t answer those questions tonight. Basically, tonight is for questions on
construction. Those kind of questions
can be answered by the Finance Department.
HALL: I can comment on that briefly. I know that if you have existing sewer
installed, you will not pay anything for the new sewer installation.
23) QUESTION: Will the pipes
be going under the road or under the sidewalk?
Where will they be placed?
HALL: They will be in the road.
24) QUESTION: How can we be
charged retroactively for something that doesn’t exist.
HALL: That is a question for the Finance Director and the
Administrator. That is not a question
for the Town Engineer and Public Works Director to answer. I don’t have that information to give you a
proper answer.
25) QUESTION: I missed what
you said in the beginning but you said this project can go into April?
HALL: Should be about May.
First or second week in May to be off Turner Road and you will have a
binder coat put down. Then he is off to
another few projects around the Town.
Expect him back in like October probably to put the top on Turner Road.
26) QUESTION: What can be
done in the mean time to improve the road surface which is deteriorating daily?
HALL: First of all that is a temporary surface that is up
there right now. He has got to maintain
the surface. The surface has to be
passable. It has to be safe to have a
fire truck, police truck, rescue wagon go down to make a call on Turner Road.
27) QUESTION: Is it
considered to be passable in its present condition?
HALL: Yes it is.
28) QUESTION: We live on
it. It has got to be passable and it is
barely that now without destroying your car.
HALL: Okay. That temporary patch that goes down is not free. Everybody pays for it. It is not free. So you’ve got to cut it off. You have to have a limit where that is good enough for a
temporary situation. Safe for police,
fire, and rescue. And that’s where we are coming from. I mean if we want to force him to grind it
up and put a binder coat on, similar to the other main roads in Town, that’s
going to cost the Town money.
Typically, you don’t do that.
29) QUESTION: What’s it going
to take to have him just patch the big holes?
HALL: He is charged to patch those big holes to fill in the
pot holes. He has to maintain the
temporary patch that is out there and maintain the condition of the road to a
level that the police is happy with,
the Public Works Director is happy with, and the Fire Department is
happy with.
30) QUESTION: So how often
is that inspected?
O'LOUGHLIN: It gets inspected daily and if any resident
notices a pothole they can notify our office.
We have cell phone numbers of the people who work for Dicon. If its noticed over the weekend, all of us
are local, we drive the road. If we
notice anything, we call them directly.
We get them down whether it is a weekend or a weekday. It is my opinion right now that the
temporary patch is in pretty good shape.
I drive the road almost every day and if we notice anything, we call
them. The police have their numbers so
if on a weekend a call is placed for a bad situation, they will be notified
that they have to come down and respond.
31) QUESTION: It appears to
me that the Town is stalling in telling the residents of Turner Road what it is
going to cost them to put this sewer and water in. Someone in the Town must know what it is going to cost. Every time you talk to someone, everybody
says I don’t know, talk to this one and that one. Some of you people must know what it is going to cost the
residents to install this water and sewer on Turner Road. You can’t get an answer from anybody.
COUNCILMAN PAUL RODERIQUES:
I’ll answer that. The residents
of Turner Road, some of them, came to a meeting and said when they were digging
it up, “we didn’t ask for sewer” but you are putting in sewer. The drainage needed it and we weren’t sure
it needed drainage. And then they said
what we really needed was water because I think there were ten houses or so
that had bad wells and, Paul you are one of them. So we said you know what, the new Council takes over and says you
know what, it does make sense, while the road is being dug up, to put in
water. At that particular time they
said, we are willing to pay for water – the ones that were there, not all of
them, some of them. Well as things progressed
at the next meeting or two, some of the residents came back in three weeks, the
same residents, said we are not willing to pay for the water. So right now the Council is struggling with
whether we should charge them the full rate.
There was no hidden agendas. We
said if you’re going to get water pipes, you are going to pay for it. That was right up front. But how were they going to pay for it? We didn’t have a mechanism to charge them
like we do frontage on sewer. We didn’t
have that because Newport runs the water department and controls all the water
lines in Middletown. So we said let’s
get some enabling legislation so we can charge for water because we want to be
able to give you the services. I’d love
to be able to stand up here and say I’ll give you the services for free but I
can’t do that. At this day and age, you
can’t afford to do that as a Town. I
can probably speak for the other six council members, we’d love to do
that. We just can’t afford to do that
as a Town. So what we are saying now
from a time standpoint, they put enabling legislation date back to this new
fiscal year which started on July 1, 2002.
So that it encompasses the whole budget for this fiscal year that we are
in. So I can tell you this, name some
of the councilmen that are in favor of only changing a certain percentage, and
some might be in favor of charging the whole thing, and some might be in favor
of charging none. Nothing. I can’t speak for the council, I can only
speak for myself and really tell you I’m trying to give you what is going on
with the payments and everything. We are waiting to get the enabling
legislation and once that goes through then we will have to decide as a group,
as a Council, and sit down and figure out what we are going to do for you. But I know as a point of fact as for making
a decision as a council person responsible for the whole town - I understand the situation at Turner Road
that it was going to be free. But I am
certain we are going to do the best we can for the residents and I sympathize
with some of the people that have to pay for sewer and water at the same time
and put up with the conditions that weren’t right from the start. We’re trying to make improvements and we’re
trying to do the best we can.
HALL: If you’re interested in what your final charges are
going to be. There are two charts that
are outside the Finance Department in the Town Hall. You can go down there and find your plat and lot number and there
is the sewer charge and the water charge for each lot listed.
32) QUESTION: What is the
plan for the paving of the road? Is it going
to be scraped? Over the years there has
been blacktop on top of blacktop. Some
of the areas on the lower end in a heavy rain water comes right over the top
into the property.
HALL: Those areas will receive special attention. Your driveway is wet, I know that and I
think there’s another driveway up there that has the same problem. We’re going to lower the grade a little bit
and get the water to back flow over there into your driveway. There will be a two inch wide lip. It will be ground and reclaimed, reshaped,
compacted. Then we will put over two
inches of binder coat down. That binder
will sit for a six month period so we can find out if there is any movement or
if we have any problems. As far as
laterals, we can address that with the finish coat. The finish coat will be on probably October-November this
year. That’s dependant on the schedule
of the contractor.
33) QUESTION: I was just
going to ask are driveways being addressed?
HALL: Yes, in fact we are installing a catch basin at your
driveway.
34) QUESTION: Following what
Mr. Ardito said, when we have the final coat put on that road are we avoiding
something like High Street I hope. Are
we going to have another patchwork quilt?
Is Turner Road going to be another patchwork quilt like High Street?
HALL: It is not planned to be. It is not going to be as far as my control goes. There is a problem on High Street that
wasn’t addressed and that is what happened.
You ended up with patch work.
This road - we don’t plan roads that way.
35) QUESTION: Just from
residents standpoint when I think about roads being major construction. To me that is a lot of work involved. So I look at it I think right away initially
what has happened there, the initial condition of the road was horrible. I know it was weather driven but we got on
the contractor and they got much better but from a quality standpoint when this
is a completed project I’m thinking it'll end up with, Theresa touched on it,
not like High Street but like Wyatt Road.
And I know you do compaction tests now but could you let the residents
know what the procedures to make sure that things like this don’t happen and if
they do happen, how long do we hold that contractor responsible for that work
before we start releasing bond money that we hold back in case something does
happen if they don’t fix it. Can you
run through that process a little bit for them.
HALL: The quality control that is on Turner Road and the
rest of the project is that we perform compaction tests. We have a consultant that comes in and does
compaction tests when we ask them for them.
The minimum required number of tests is based on how deep the trench is,
how long the trench is. If we see the
contractor not putting the proper effort into compaction, then we automatically
call our testing agency. They come up
and do a test right there. We find out
whether it is good or bad, right on the spot.
We have them take it out and remove some material. As far as the finish grades go, we are going
to pay attention to the finished grades and make sure we don’t have any
sags. Catch basins have to be set at
the right grade. That’s what I’ll say. We have done a fair number of roads that
have come out good and acceptable.
36) QUESTION: How long do
you hold that bond for?
HALL: The bond is held for one or two years. I’ll have to check to see precisely what his
bond says but it is at least one year from the time that we accept the project
which I’m guessing is going to be some time about October-November this year.
37) QUESTION: And you keep a
portion of that money? You don’t
release the whole bond?
HALL: We keep 5% of his earned money for six months. There is a performance bond that the
contractor has sitting in the Town Hall right now that expires either in a year
or two years, I’m not sure which one it is.
It depends on who the bonding company is. A year or two years and that is from the time we accept the project.
38) QUESTION: I think we can
show an example of what went on at High Street where we still have the bond and
there are things in the works to rectify the problem
HALL: That is correct.
We still have the bond on High Street.
We still have a fair amount of …..
QUESTION: The same thing could happen on Turner Road
HALL: Earned the
cash. The guy has earned the cash but
we keep five percent. Every time he
gets paid, we keep five percent.
39) QUESTION: How about the
sidewalks on Turner Road? Are they
going to be done?
HALL: Sidewalks are not part of the project
40) QUESTION: What about the
grass on the shoulder of the road
HALL: That will be done in the planting season like April to
June or so.
QUESTION: Is that about when the first coat is put on?
HALL: Yes. Yes.
About the time of the first coat.
But he has a window in which he has to plant the grass seed or he
doesn’t get paid for it
QUESTION: When does the window end?
HALL: It is March 15th through April 15th.
41) QUESTION: Are there any
traffic calming elements that are going to be constructed to prevent it
becoming a throughway again?
HALL: There isn’t any real traffic calming elements. No.
We will have white stripes on the travel lane and the new yellow center
line, but there are no plans to add any traffic calming elements.
42) QUESTION: Obviously you
are going to have a crosswalk at Gaudet.
Right?
HALL: Yes
QUESTION: Has there been mention of a flashing light right
there to slow down traffic with the Council?
I’ve read things in the paper.
O'LOUGHLIN: Right now we are in the process of putting speed
limit lights, 20 MPH, on Aquidneck Avenue.
We have spoken to the School Department about looking at Turner Road. So if it is something the residents are
interested in as far as having the same flashing lights at either entrance and
that would slow traffic down, you can either bring your concerns to my office
or you can forward it to the Town Administrator or the School Department. We have begun talking about it – where the
front of the school is critical first.
Turner is a town road and we can do that a lot easier internally, within
the Town we can address those concerns.
43) QUESTION: They do fly
down there and heavy trucks go through there too. Electric corporation trucks and heavy trucks cutting through to
go to Newport. Can we make it no thru
trucks?
HALL: I’m not sure we can or not. We’ll find out. It is a
good question. I know there is a
concern with that street because it is used by the nursery. The nursery has some trucks.
QUESTION: The nursery trucks seem to go the speed
limit. They seem to respect that
neighborhood. It’s the utility trucks. There are dump trucks. There’s a lot of commercial vehicles. There are charter buses coming through
there. They don’t need to be in a
residential area.
O'LOUGHLIN: The only thing that we can address with those
kind of concerns is through the Police Department. What happens is if we go through the Police Department and then
bring it to the Council then we can look at any of those concerns as far as ….
There has to be an ordinance in place before we can actually make a change on
that road. So if you do have any
concerns again you can either forward them to my office, we can put it
together, or put it together as a group.
We can take it to again the Police Chief can investigate what we can and
can’t do and then propose something to the Council so that the Council can vote
on Turner Road as far as ordinances.
44) QUESTION: One thing you
can do is enforce the speed limit. A
short path becomes a lot less attractive.
I think the problem you have is that a lot of people know the short path
– not only people who live here but people who have business passing
through. If it becomes not such a good
thing, it also becomes known very quickly.
The law is already there. There
is a sign up.
QUESTION: Would it be too much inconvenience for us to put
3-way stop signs at Ward Avenue and Ward Street?
O'LOUGHLIN: And that falls under the same thing. The Police Department has to evaluate it and
if they feel it is worth while then we can propose an ordinance to the Council
and the Council would vote on it…………….. Because there has to be an ordinance in
place or it doesn’t hold any weight. If
someone violates a stop sign that doesn’t have an ordinance, they can’t
actually be fined. We have to make sure
there is an ordinance in place before we begin putting up stop signs.
HALL: We’ll look into it.
45) QUESTION: As far as
weight limits go, they would have to be pretty substantial. We have tractor trailers come in.
HALL: Right
46) QUESTION: What is the
plan for Turner Road and Green End? Are
they supposed to square that off?
HALL: That has been talked about. I’ve done a little bit of work on it as far trying to realign how
the traffic intersects out there and look at some of the sight vistas coming
down Green End Avenue or rather looking up Green End from Turner. It is not part of the contract right now. I'd like to say that it is possible to entertain
maybe get a consultant involved and take a look at some of the improvements at
that intersection.
47) QUESTION: If it is
cheaper to do it now, can we get with the contractor and modify the contract
and get it done? I know there will have
to be some decisions made, which is fine.
HALL: We would have the contractor modify that intersection
and I would guess most likely at no cost.
You're going to have grass where you were going to have asphalt. Just restripe it and realign it but I want
to be sure this intersection works better than what is out there right
now. We have looked at it from two
different directions, some zoning issues out there, and that's where we are
right now. It is going to go unlooked
at.
48) QUESTION: I have a few
questions on the bid specification. Why
did the bid specification include tree removal?
HALL: The tree removal was included in the bid spec and the
scope of the work basically was in the scope because existing storm drain runs
down Turner Road right now underneath a fair number of trees. So in order to replace that storm drain we
would have had to remove the trees to get the storm drain replaced. After we talked with the tree warden, we
decided not to do that.
49) QUESTION: A lot of those
trees were just planted for a couple of years.
Those were going to be reinstalled, the same trees?
HALL: No, they were going to be removed and replaced.
50) QUESTION: Why wasn't the
tree warden consulted prior to the scope of the work?
HALL: I don't know.
51) QUESTION: When the RCP
pipe was bid why wasn't there an alternate bid for the SDR pipe or an addendum
price?
HALL: Because the price between
the SDR-35 pipe is more expensive, the RCP pipe is cheaper but it is more
expensive to install the RCP pipe than it is to install the plastic pipe. And also we have learned from other
projects, the plastic pipe becomes sometimes difficult to get in the larger
diameters, 24 inch and 18 inch diameters.
We ended up substituting some pipes in a little less quality for those
size diameters in other projects. So I
wanted to be certain that we bid the concrete pipe, in case the plastic pipe
was not available in those large diameters.
And also the plastic pipe hydraulically is superior to the concrete
pipe, so plastic pipe is my preferred pipe.
52) QUESTION: Why can't that
be bid at two separate prices? If you
got it, you got it. If you don't, you
don't. As far as the total bid goes.
HALL: We could do that.
QUESTION: I know that the labor is quite more expensive on 8
foot sections rather than 13 foot sections and you're talking a couple of men
and a machine to put in the cement pipe where you don't need that to put in the
plastic pipe.
HALL: That's correct.
So the cement pipe is labor intensive.
The plastic pipe is more expensive per foot to purchase that pipe.
QUESTION: Follow-up question please. Next contract which I am really worried
about, do you intend to make both pipes bid or are we going to do it the same
way in future contracts, bidding one pipe and using a different pipe? Because it is unfair to various contractors,
there may have been a lower bidder bidding on the plastic pipe than on the
concrete pipe. But you only required
them to bid on the concrete pipe and then we had the plastic pipe put in
without any addendum or alternate bid.
So I'm asking in future contracts are we going to do it the same way of
one pipe bid or are we going to have both pipes bid?
HALL: We could do it with both pipes. After this contract we have seen that we
have had so much attention on the type of pipe that was bid and so on and so
forth that we may take a look at that with our new Road & Utilities
committee to see how they feel about it and I'd look to them for some guidance
on that. Every bidder that bid this
project was told the exact same bid specifications, type of pipe to bid and so
on and so forth. It was all the same,
everybody was right there.
QUESTION: Everybody bid concrete?
HALL: That's correct.
53) QUESTION: Question on
the ledge removal with this contract.
That was a zero bid item on the contract overall. It is understandable that you don't know
what you are going to run into, but there is a price required on the bid. Is there some way to qualify the price that
you will pay for removal of ledge from a project before the bid goes out. If the contractor wants the bid, he will
accept that price, I mean a fair price..
Because we got from $62 per cubic yard to $750 per cubic yard and that
is a big chunk of dough if we did hit ledge, so far we have been lucky.
HALL: I don't know.
I would again get some guidance from somebody else and find out whether
or not you can actually give a unit price that a contractor would have to accept,
to accept the project.
O'LOUGHLIN: It is
also difficult for a contractor to give a fixed price on something they haven't
seen. Because some piece of ledge is
going to pull up easier and other cases it is going to be solid rock. We have the experience working with contractors
that if we look at a situation and know that if we look at a situation and we
also have people out there on a daily basis and we're watching them do the
ledge removal, we'll see what the intensity is from that and we're going to
negotiate that back with them. And
obviously if it is a situation that they are taking a machine and they are
pulling out some pieces of shale and other things, of course that is not ledge
removal. But it is difficult because
you could have a situation where you can have one rock that takes you 20 hours
to break up and you can have other situations where you have three times the
quantity but you could remove it in a short period of time.
54) QUESTION: There was a
big boulder in front of my house that was dug out and push across the
street. It took them 20 minutes to
remove it.
O'LOUGHLIN: My feeling is that if we evaluate the effort
that they put into removing it and if it takes them 20 minutes, we can say to
them, hey, we're not going to approve a change order for $10,000 for something
that took you 20 minutes. But if we can
see the effort and we can evaluate the effort, that is probably the best way to
do it because the contractors that are going to be bidding and if they are nervous
about what they may uncover in that road, that unit price is going to be a lot
higher or they are going to take some risks.
It is probably a better situation where we actually evaluate every price
or every area. We can say that we have
five cubic yards that you are going to remove, we are going to be there when
you do it, you can't remove it without our presence. We will see what kind of effort goes into it, what type of
machinery goes into it, and then we will evaluate the change order so it is fair
to everybody.
55) QUESTION: Follow-up. I think that is a perfect solution during
construction. My problem with ledge is
the bidding. By having a quantity of
zero in the bid spec, you allow the contractor to put in an exorbitant price
because it does not impact his final total.
It will not eliminate him as a low bidder. If you look at Dicon's bid on ledge, they are completely out of
sight on the average of the other guys and certainly way out of sight of the
low guy. That is because Dicon's is low
bidder and there is zero quantity in the spec of ledge. So he puts $750 per cubic yards. I suggest that the zero quantity on the spec
is what is wrong. I know you can't
estimate how much ledge is there. I
know we don't know what you are going to find until we dig, but in terms of
defining who is going to be low bidder, you can specify 1000 cubic yards or 100
cubic yards and let them bid on it. And
if Dicon were to bid $750 per cubic yard for 100 cubic yards, they wouldn't
have been low bidder. They were allowed
to bid this ridiculously high price because of the zero quantity. That is what is wrong in the spec and my
question is, as I say I am more worried about the next contract than I am now,
what are you going to do in future contracts?
Are we going to be more careful in regard to ledge quantities?
O'LOUGHLIN: We can put a minimum quantity amount in and just
so it does put a dollar amount effect to it.
The question is we do have to come up with a better formula to do that
to just keep it fair but most likely we will get a lower price from that
bidder.
QUESTION: Yes. There
is no way Dicon would have bid $750 per cubic yards.
O'LOUGHLIN: We also have to look at the minimum quantity we
choose. Because we have to make it so
that if they highball it, it is going to make a difference with their overall
competitive price with everybody else.
56) QUESTION: You realize
that removal by machine is not considered ledge? If you dig it out with your machine whether it is a hard product
or ripped up, it is not ledge.
O'LOUGHLIN: Exactly.
QUESTION: I have a follow-up on that. That boulder was dug out with a
machine. Was that boulder paid as
ledge?
HALL: Yes, the boulder was paid as ledge. We paid for one yard removal of that
boulder,
QUESTION: A machine took it out?
HALL: It is ledge.
The way I understand it, he spent extra effort removing that
boulder. The effort cost him time. He called it ledge. There isn't anything that says that if you
can dig it out with a machine. What if
it is shale type material and he can dig it out with a machine but he has to go
a lot slower? It is not like he is
digging out that nice fill.
57) QUESTION: Uncle Sam say
if you take it out with a machine, you don't get paid for ledge.
O'LOUGHLIN: That's not true.
HALL: If you say Uncle Sam says it, send it over to me in
writing. We'll entertain it, we'll put
it in our next specification.
58) QUESTION: Just a
thought. Most of the towns in
Massachusetts now go with it has to be a yard minimum. In Massachusetts they are pulling boulders,
around here we have ledge. When it
comes to a point to measure it up, if it's one yard they pay for it. If it is anything less, they don't.
HALL: So in Massachusetts the rule is if the boulder is
greater than a yard it gets paid for.
If the boulder is less than a yard, he doesn't get paid for it.
QUESTION: Well I dug one of mine in Portsmouth and I didn't
get paid for it in Portsmouth.
HALL: In Portsmouth Manny.
59) QUESTION: How much did
that actually cost the Town?
HALL: One yard. $750.
We measured, it was about a two yard boulder.
60) QUESTION: And my point
is that same cubic yard by any other contractor would have been $300. Now that's only $450 more but Dicon was
allowed to bid an exorbitant price on the zero quantity. So please in the future, don't put bid specs
that way. We don't know what kind of
ledge. If we hit ledge on this road all
the way down, Dicon would bankrupt the Town of Middletown because of that one
item.
HALL: That's what
you think, but if we hit ledge all the way down that storm drain that's going
in the ground, all I would have done is I would have taken it and would have
started taking out the trees. That was
my thought. That's why I knew that the
storm drain was going to go in with probably zero quantity of ledge. Because there is already a storm drain in
the ground.
QUESTION: How about the sewer ledge?
HALL: The sewer was unknown, I will say that. 1800 feet.
61) QUESTION: Just fix it on
the bid spec. Don't let a contractor do
this. That is all I'm asking. Don't have zero quantity bid items, it just
allows a contractor.
HALL: It is a good point and we take it.
62) QUESTION: Do you have
any idea when this is all going to be done?
Are you going to be working during the summer?
HALL: We won't be working during the summer. The plan is to have the contractor off
Turner Road sometime about the middle of May.
Hopefully sooner.
QUESTION: Is that when the 180 days stop?
HALL: The 180 days
excludes weather below a certain temperature, if it's raining. He gets credit for those days.
O'LOUGHLIN: They are not calendar days, they are working
days.
QUESTION: So May is the latest you say?
HALL: Depends on the weather and no unusual conditions, he
should be out of there about the middle of May. That will be the binder asphalt down. Then he comes back in October-November and puts the top asphalt
down.
QUESTION: So he won't be there July through September?
HALL: If he is still there in July or September, there is a
big problem. There is something that we
did not foresee in the ground there. I
think you will be safe in July, August, September.
63) QUESTION: If he gets
rained out on Wednesday, what is to stop him from working on Saturday to meet
the schedule? I haven't seen that
happen at all so far.
HALL: Well, Saturday would require overtime for the
inspector, the police detail goes to double time or whatever it is. He has asked to do that and we have told him
what he has to do to work on holidays and weekends.
64) QUESTION:
The payment for the police comes out of the Town budget or out of the
contractor?
HALL: If it is going to be a holiday or
a weekend, the contractor pays for it.
If it is going to be during the week, the Town pays for it.
QUESTION: So basically there is no way he will work on
Saturday if he had to pay for Police!
O'LOUGHLIN: That is up to him. He has asked for a holiday.
We gave him the rates that he would have to pay for someone from Public
Works and then we gave him the rate on what he would have to pay for the Police
detail and he chose not to work for that holiday.
65) QUESTION: Why did it
take so long to patch the road once they had to re-rip it up and did it
out? They did the center road pretty
quick, they got extra trucks and all that stuff. But when it they got to the side of the road, it took forever and
it was only partial days too. Two hour
days, four hour days and we had Police details assigned there when they worked
partial days.
HALL: I don't know why it took him so long to patch the
road. I can't answer that.
66) QUESTION: It was exactly
a month. You answered the last question
that the Town had to pick up the Police detail fees. Well, the job was shutdown on December 13th and he finished
January 10th that the patching was done.
So that was exactly one month and the financial report shows that we
spent $10,087 just for Police. Is that
going to be reimbursed because it should have been done right in the first
place when they did the road, not to dig it up again.
HALL: We can look into that.
O'LOUGHLIN: Just to let you know. Whenever they do any change orders, it comes in through
Warren. Warren and myself review
it. We sit down with the Finance
Director We're very critical of the
reviews. If he's asking for any money,
whether it's any money that was worked on or any change orders, we go through
it. We're not afraid to reject
invoices. We're looking out for the
best interest of the Town.
67) QUESTION: Is it possible
not to have two-man crews in on these days where the Police have got to man the
thing?
O'LOUGHLIN: These are the things that we can look at.
HALL: That has been an administrative decision to pay the
Police out of the Town. I don't know if
it comes out of the general fund or what fund it comes out of, but to pay the
Police out of the general fund. What we may do in the future, looking at future jobs, is
say that the contractor will be responsible to pay the Police detail and make
him bid those hours.
68) QUESTION: Right now that
amount from the time he started the job until the end of December, we have
$33,000 in Police details and the way this job is going we probably will end up
with over $100,000 Police fees.
HALL: I know it adds up.
69) QUESTION: Do we really
need the Police there? Why don't they
give them the option of using flaggers, certified flaggers?
HALL: They were given the option to use flaggers. That question was raised in the pre-bid and
we addressed it that they could use flaggers.
70) QUESTION: Are we going
to have them clean up daily? There is
tracks coming out of the nursery where they are storing the stuff. It is horrible up and down the roads,
unbelievable. I know on other roads it
has to be picked up daily if your have tire tracks coming out into the highways
and stuff like that so you don't track some dirt down the road. And there you have stone on the road that
tires pick up and other things. I was
wondering why it is not getting enforced any better. They work until it is time to quit and then just go home. Nothing is done.
HALL: I know he had a sweeper there. We will take a look at that and see if we
can have him do a little better housekeeping.
71) QUESTION: I am curious
how they are going to preserve the bituminous curbing along the sidewalk at the
school. Are there laterals going in
toward the east?
HALL: There will be water laterals cut across the sidewalks.
72) QUESTION: It seems to me
that a significant highway project such as this, that whole sidewalk should
have been rebuilt, especially with a public school right there. It is hard for me to believe that they are
not doing anything on the sidewalks.
HALL: Again the sidewalk question comes up. It was an administrative decision not to do
the sidewalks. The lip curb is a bid
item. I believe we are going to put a
new lip in the whole length and on the other side where we need it we will put
Cape Cod curbing. Nothing on the
sidewalk - the sidewalk stays right where it is. Today.
73) QUESTION: Let's go back
a few questions regarding working on Saturday.
You said the contractor can work on Saturdays but he would have to pay
his men, the Town inspector overtime, and a policeman. By working on Saturdays, wouldn't that
expedite getting this road done? And
who gives the authority on that, on working on Saturdays? Does he come to you, the Public Works
Director Mr. O'Loughlin to work on Saturdays?
O'LOUGHLIN: Yes.
HALL: Yes, he either comes to me and I take it to Tom or he
goes to Tom and Tom will bring it to me.
74) QUESTION: Has he come to
you and asked to work on Saturdays?
HALL: He has asked to work on the last holiday that we
had. Last Monday, but we told him no.
O'LOUGHLIN: We told him its his decision based on these
figures for paying overtime. In other
words, if he starts getting close to the date and obviously if he goes past a
reasonable time and Warren has a log of every day as far as temperature, days
that he can work, days that he can't.
So we're keeping track of where we stand on a calendar on his work
days. So it is an issue that we can evaluate
at the end. If he takes the contract
and he knows he has a set time while there is not penalties, if he doesn't
finish in a reasonable amount of time, we can again attach his bond. There are other methods, we just don't have
to just have something in place if you don't pass a set. So if he decides to work on Saturdays
because he is getting close to that point, he would still have to incur the
cost from the Town. If the Town decides
to work with him and address it, it would have to be a decision that would
either come from a recommendation that Warren and I make to the Town Administrator
and may make its way to the Town Council.
75) QUESTION: How many days
have you allocated to this job? Work
days?
HALL: I'd have to look that up. He started October 7th, that was his first day out there.
QUESTION: How many weather related days have we lost?
HALL: I don't know that.
I don't think he has lost a whole bunch, maybe ten. But I'll get back to you on that.
76) QUESTION: Is there any
reason why he doesn't have three groups and work different areas of the road?
HALL: No, there is no
reason why.
QUESTION: We don't really control that do we?
HALL: We don't control that.
O'LOUGHLIN: Legally we can't tell the contractor means and
methods. What we do is what I say. We have a count of the number of work days
in the contract. We look at every day
that he can work. If he goes, again its
got to be considered a reasonable amount of time past that date, it is going to
be a situation where he would lose so much money. Anyway it would put him in a bad situation financially and then
we would have the bond for the cost of the project. So if it gets into a time issue on Turner Road, we're not going
to allow him onto Wolcott if he is not doing a good job or not finishing up on
Turner. So it is a situation, in the
sense of being first on all these projects, you actually have the largest
benefit compared to the other sites. So
there are mechanisms in place to make sure that obviously Turner Road has to be
in very good shape before he is even allowed to start the other project. If he wastes his time, it is ultimately
going to cost him money.
77) QUESTION: There have
been days when he had two men piddling doing nothing. They count toward his work days?
Right? Okay, so when he is piddling along with two men driving up and
down the road doing nothing, he is actually losing days. We are not adding on some extra days for him
as a result of this period of time?
O'LOUGHLIN: No. We are being very critical with him as far
as checking the days he would work. In
many conversations we have had with him, he calls in checking the conditions in
Town. There are a lot of methods that
are in place right now that we obviously are checking his work, making sure
that he is doing it and that's why you had some of his time where he was
re-patching because there was a decision Warren and I made that his patches
weren't holding up and that we told him he had to correct it. So then he lost some of his calendar
workdays because he was repairing his own work. The depth of the frost right now is going to be difficult but in
some ways the cold patch is holding up better in this weather.
78) QUESTION: I have a
number of questions and have been waiting for most of the others to ask
theirs. First I would like to apologize
for being late. Secondly I would like
to thank you for this meeting. This is
refreshing. I don't think the previous
administration would have had this meeting to listen to us. So I would like to seriously thank you and
I'm looking forward to better days with this administration. Now for some maybe not so easy
questions. On the bid selection, did
Dicon's bid of a nickel per cubic yard for trench base material raise any questions? What about his price of a dollar to readjust
a mailbox or a nickel each to adjust an electric manhole or water gates? Shouldn't these bid items raise a red flag
in terms of quality of work of this guy?
HALL: We asked him about specifically his road
material. The way he explained it to
us, he thought as you grind and reclaim that road, he was going to grind 12
inches, it was going to blend together, and that was going to become his 12
inch base. That was his explanation.
79) QUESTION: Okay you did
ask him. Before awarding the bid to him
or after the bid was awarded to him?
Did anybody, be it the Town Council or Administration, question the low
bid before the bid was awarded?
HALL: Yeah, I believe we did. We met with Dicon. We,
being myself and the Town Administrator.
QUESTION: And they gave a satisfactory answer to those
ridiculous prices?
O'LOUGHLIN: One thing though. Those ridiculous prices cost him a lot of money right now because
we in turn came back and said your gravel, your base, is not working in these
trenches. So it is a double edge sword
for the contractor when they take these risks.
That risk is not paying off for Dicon, I can tell you that.
80) QUESTION: I think we
knew that from the beginning. You can't
buy air for a nickel per cubic yard.
Okay. Dicon's bid for erosion control
was also extremely low. Didn't anybody
suspect that these low bids were going to be an indication of poor performance
by this company? And are we going to
look at future contracts with a more diligent eye when we see these low
individual bid items, especially by the low overall bidder? Because I think it is indicative, certainly
on erosion control. His erosion control
amounted to none around his dirt piles next to my neighbor's yard and it forced
it and tipped the fence over as a result of no erosion control. I guess you could bid a little amount for
erosion control if we are not going to do it.
But I assume he had to do it.
But they are there now, now that the fence is down. Why weren't they there on day one? I think on future contracts we have got to
when we see these red flags of low bid items, especially if it is going to
impact performance, we are going to have to some how nail the contractor down
before we give him the bid to explain why he is bidding so low and is he going
to do the job. Because yes we may force
this guy into doing it and we may wind up forcing this guy into bankruptcy as a
result of his ridiculous low bid.
Okay. Was there ever any
consideration of not selecting the low bidder because of these apparent
inconsistencies and, more importantly, in the future will we be looking for a
better selection process that will allow us to select other than the low
bidder? And what do you think about
selecting other than the low bidder?
COUNCILMAN PAUL RODERIQUES: I'll gladly answer that. I don't think necessarily that the low
bidder is always the best quality.
Based on history, on a whole other project that I was not in favor of,
because of past poor performance. These
are things we need to look at. I know
this particular contractor had done work before and it was satisfactory. Yes, this whole project is going to bring a
whole new light and it certainly educated me on the whole bid process. So I think certainly there were some good
points made by you and the other folks in the room that we need to take a much
better look and hopefully now with the new Road & Utilities commission we
will look at things like that.
81) QUESTION: Moving past
the bid selection phase into construction, Dicon began this project up at Wyatt
Road with sewer and for the base of the pipe they began using stone dust. Why did the Clerk of the Works okay this
material until it was finally stopped when it was pointed out by a taxpayer?
HALL: I don't know if it was finally stopped when it was
pointed out by a taxpayer. I think it
was stopped when we put an end to it.
And it was very brief that he tried to use stone dust under the pipe -
it was two lengths. The reason that he
asked permission to do that, he gave his reasons why he wanted to do that, we thought
they were good reasons. It turns out
that after two lengths of pipe was in the ground - 26 feet of pipe in the
ground - we said no. You're not putting
the effort into preparing that base for the pipe to sit on, no more stone
dust. The reason the stone dust was thought to be a better
product than stone or gravel that we typically use under a pipe is that gravel
or stone actually has voids in them and when you get the weather we have around
here and you have got the soils around here, the water gets down to your trench
and what happens is that once the water finds a place to run, it gets into that
gravel and it has a place to run, it just runs right down your trench and it
takes all that surface water along with it.
We have experienced that problem on other projects, we thought the stone
dust was a good idea because it is a lot less permeable or it has a lot more
resistance to let water flow through it.
We tried that product but we just didn't like the effort that they were
doing with that product. That's where
we stopped them.
QUESTION: You will probably not use it again in any other
project?
HALL: I don't think so.
82) QUESTION: Stone dust
compacts very solidly. I'm not certain
that a solid base without the natural give of the gravel is what the pipe
needs. It seems to me that you would
want a little bit of give for expansion and contraction for the pipe and stone
dust really compacts like a rock.
HALL: No, the gravel is actually a structural requirement by
most of the pipe manufacturers to keep the pipe from what we call egging or
compressing. If the pipe is not
properly bedded then what happens it haunches out.
83) QUESTION: Why was Dicon
allowed to create mounds of dirt without sediment control barriers? Why wasn't sediment control used at the
beginning and why did the Clerk of the Works allow this?
HALL: A good question.
I'll just say that at this point that area has been corrected and we
will pay closer attention to those details in the future.
84) QUESTION: And this is
the biggest bugaboo, why were the pipe trenches allowed to be uncovered with
asphalt for three weekends in a row, maybe more, resulting in that horrendous
condition of the road and why didn't the Clerk of the Works compel the
contractor to cover these trenches as is required by the specifications?
HALL: The only answer that I may have for that is on those
dates, those particular three weekends, was it temperature or rain?
85) QUESTION: He was going
300 feet a day for five days, break for the weekend, uncovered trench. I mean filled in with his muck and stuff but
no asphalt. That is how he did the
entire project until you finally stopped him.
He never put asphalt on top of the trenches.
HALL: I don't know.
I'll go back and check the records.
I don't know. He may have been
sensing a problem with that material that he was going to put his temporary
patch on anticipating that if that patch started to break up, he wasn't going
to get paid for that patch. Typically we are pretty strict on the seven days. We will let a trench sit for seven days,
then we will make him put a patch on it.
86) QUESTION: The old drain
pipe that is in there, are they properly sealed? I'm worried about having an open trench where water can wash in
and wash the roadway away of if some toxic material got in at one end and come
flying up the other end. When we broke
all of these trenches for putting in laterals, have we properly sealed them so
we won't have a long range problem of the road bed eroding away?
HALL: We are keeping
accurate measurements. We're keeping
accurate notes as far as which ends of the pipes have been sealed and which
ends of the pipes have not been sealed.
And we will go back and seal those ones that have not been sealed. So the answer is yes we are. All the breaks and all the manholes have
been documented.
87) QUESTION: Let me preface
this one by saying that I don't have any problem with trucks and materials
stored on Hoogendorn property and I don't have any problem with any kind of
arrangement that Hoogendorn has made with the company for doing that. I do have a concern if the Town got in the
middle of negotiations and offered something, so my question is, is the Town in
any way responsible for the storage of material on Hoogendorn nursery?
HALL: My answer is no, we are not. We have not had any negotiations with the Hoogendorns. We have nothing to do with any compensation
between Hoogendorn and Dicon or Dicon and Hoogendorn. What I say is that the Town has no responsibility to restore or
repair the damage that has been done over there. That is my opinion.
88) QUESTION: One item in
the contract was Loam & Seed and I know what that is for I think. Where they tear up the side of the road on
grass, they will replant it and repair it.
But that bid was for the entire section when we were going to remove the
old drainage pipe which exists all along the football field. We did not do that so the amount of grass
and loam and seed and effort is minimal.
It is just whatever mess they made by the side of the road because they
dug in the street. They bid X amount of
dollars for a lot of loam and seed which they are not going to use now. What happens to that money? Do they get paid for it or do we get that
money back?
HALL: They don't get paid for it. The money doesn't pass any hands. If they don't do a unit square yard, they don't get paid for that
square yard.
89) QUESTION: There is a lot
of damage done on the other side of the road too when they were dumping the
dirt and picking it up and backfilling and stuff. Is that going to be all reseeded at their cost or is that going
to be added to their square footage?
HALL: He's responsible for all the damage he has done.
O'LOUGHLIN: We have been very critical. The guys are out in the field on a daily
basis checking these things out. If
they note something that needs to be reengineered, we keep track of it. If he submits an application, we will have
our records in place. We will check our
as-built information against his as-built information.
90) QUESTION: Does that
include also the trees that got damaged.
O'LOUGHLIN: We will look at any damage caused by him. We are in daily contact with our tree
warden.
91) QUESTION: Are we going
to leave tees on these water lines to bring water lines across to the side
streets so we don't have to dig back out again?
HALL: There is one side street that we are going to do that
for and that is Ward Street. Ward
Avenue is going to get a tee and we're going to run an 8 inch main right up
Ward Avenue and tie into Columbia.
92) QUESTION: When we do
projects like that when they brought the water in before to solve Billy
Cristi's problem a couple years ago or whenever it was from Honeyman up Ward
and down Columbia. And now we are doing
Turner Road and going into Ward to meet Columbia but we are leaving a fishhook
so to speak on Ellen and Ward. It
fishhooks around the other side of Honeyman.
To me just in the future if we are going to do things like this, it just
makes no sense why all these people have water and we leave out ten
houses. It makes no sense at all.
O'LOUGHLIN: There was.
Just reading the papers, there was a lot of dispute, conversations back
and forth on where you put those lines in.
So there was a lot of other pressures I guess in that decision.
HALL: I think the Town made a good decision on going the way
we went because instead of having ten services coming up one side, they went
the other way and picked up 23 services.
93) QUESTION: I'm not
questioning which way they went. I'm
interested in which way they didn't go.
It doesn't make any sense.
HALL: There is tees left there. The pipe is stubbed out ready to be picked up in the future. There's valves there. They are already to do it. I think it's a matter of economics.
94) QUESTION: If somebody is
connected into a line at Honeyman Avenue and the line goes down the rest of
Columbia and the rest of Ward Avenue, will they be required to pay frontage, if
they already have water from Honeyman?
HALL: That's a question to refer to Finance and the
Administrator.
O'LOUGHLIN: That would have to be addressed by the Council
and through Finance as far as any decisions.
95) QUESTION: This question
has been asked and I have heard answers at various times but I'd like to try it
one more time to try and get a handle on it in my own mind. Why has the contractor been doing so little
work in the last month and a half?
HALL: Since December 13th he has been disallowed to do any
additional work until he has repaired the road.
QUESTION: And has he repaired the road?
HALL: Yes, he has as of January 10th.
96) QUESTION: Actually the
condition of the road on January 10th versus the condition of the road at
Christmas is practically no difference.
I mean he had gotten the road to its current condition in a relatively
reasonable time - a week or two. He
should have been able to do it in six days but in a week or two he had the road
in a passable condition for all safety vehicles and my Mustang didn't bottom
out. The road was passable. It is from that time like Christmas until
now that I have seen him twiddling his thumbs and I guess I don't know why.
O'LOUGHLIN: I think there was some patching problems. He was trying to use different type of
patch. We were trying to make sure,
instead of allowing him to use anything again, we wanted to make sure it was
done correctly.
97) QUESTION: Let me give
you an anecdotal story. I'm walking
down the road on one of these days with two men on the job in this period of
time I'm talking about. These two men
were doing the following work: one was driving a machine with a large bucket
that had asphalt in it, the other was walking alongside with a shovel and they
were going up the street and they were filling in what amounted to a six inch
wide, half inch deep crack in the road which they had previously fixed. This is what I'm talking about them
twiddling their thumbs. They did this a
number of days and this is during the time when the Town had them shut down, I
think. The Town didn't turn them on
until January 10th, right or there about.
So in the middle of the Town saying that you are doing no more work,
these guys are two men with one machine and a shovel are doing what my grandson
and I could have done. And as much
needed, so I am going to pass on the question, I really never have gotten an
answer to the question as to why they are twiddling their thumbs.